What is a typical house design timeline?

I advise clients that a typical house design timeline happens over roughly three years with almost a year for each major stage;

– Year 1 Design

– Year 2 Build

– Year 3 Snagging

The first year, Design, is detailed in the Timeline image above. You can see that it takes just under six months to get the client/architect agreement in place, survey the site, design the building and make the planning application. 

Then we have a three month period for a planning decision and the appeal period (4 weeks) to complete. Assuming a positive straightforward decision is achieved, the detail design can proceed.

Where planning is not simple, and an appeal to An Bord Pleanala ensues, I would add six months to this part of the process.

The rest of that first year is taken up with detail design, tendering the project to contractors, and securing the contract and commencement notices.

The second year is construction. The third year is post-occupancy snagging to make sure everything is tickity-boo and settling well.

#ArchitalksIE #3

This is our third contribution to a shared discussion among architects practicing in Ireland, where we will discuss aspects of our services and the profession, under the Twitter hastag #ArchitalksIE

By using this hashtag on twitter, or links provided at the end of the blog, you can connect to the other architects blog on the same topic. Our blogs will be posted synchronously on the same time same day. We hope you will enjoy this format and benefit from the broad professional views and different approaches to the same issues.

The other architects views on the same topic are;

Mark Stephens http://www.markstephensarchitects.com/how-long-does-it-take-architalksie/

Zeno Winkens https://ecoark.blogspot.com/2019/10/timeline-for-dwelling.html

THANK YOU FOR READING OUR BLOG POST ON HOUSE DESIGN TIMELINES

I would love to hear your comments and if you have any questions post them in the comments below and I will get back to you. Thank you for reading my blog on this issue and do share it using the buttons opposite!

If you would like to speak with an architect please feel free to Contact Us

Also you can leave a comment or question below.

Ask The Expert!

You are invited to post your questions on this topic in the comment section at the end of the page and we will advise you as best we can….

Best in Ireland

The PassivHaus Architecture Company features in The Best Architects in Cork consumer page. We are delighted to be listed on this consumer page high-lighting the top 5 architecture practices in Cork. The practices have been assessed in terms of - Quality and Range of...

Interviews with Paul McNally architect on the Bandon PassivHaus

Interview with University College Cork Architecture Society The following are two interviews on the Bandon PassivHaus project, and links to articles in printed publications.  The next interview was with Jonathan Reinhardt from Archly.ieThe project featured in the...

A1-BER Passive House in County Cork

A1 BER passive house county cork Robert Patterson of Seek The Leak (great name!) BER assessors confirmed the astounding result of our A1 BER passive house in County Cork today. Not only that but the assessment produced a negative energy and Carbon emission value, due...

Bandon PassivHaus Site Visit

  We are pleased to invite you to this Bandon PassivHaus Site Visit. This is a great opportunity to join the Bandon PassivHaus Site Visits just as it is about to be completed, before it is occupied by the owners. We have already had many architects and contractors...

‘Building industry gets an F for sustainability’

Paul McNally was interviewed by the Irish Examiner journalist John Daly in relation to Sustainability Week 2020. The article was published online on the Examiner website on 20/5/2020 and in the Business section of the paper on Friday 22/5/2020. See this link to read...

Clonakilty Passive House

Clonakilty Passive House Our Clonakilty passive house is almost complete. This will be our most successful example of truly low carbon construction yet. Not only will the energy consumption of this house be almost zero due to the exceptionally efficient design, form,...

How NOT to Hire a Good Architect!

 How NOT to Hire a good Architect! I have written at length here on how to hire an architect, how my process works and why it is in a client's interest to follow the tried and tested method, in order to have a good project outcome. However, some people never listen,...

Open House Cork 2019 engagement

Open House Cork 2019 We were blown away by the interest in Passive House expressed during the events of Open House Cork 2019. Our participation began on Friday with my presentation on Climate Breakdown, Passive House and various projects showing its implementation. We...

Instagram Passive House De-Coded series

Passive House De-Coded now on Instagram Instagram Passive House De-Coded series; We are delighted to present video content on Instagram showing our work in progress. The idea behind this content is to talk through all aspects of the design and execution of PassivHaus...

Open House Cork 2019

Bishopstown Extension open for viewing as part of Open House Cork 2019 programme We are looking forward to opening our house extension in Bishopstown, as part of the programme of Open House Cork...